There will be a single lane closure with a temporary traffic signal on M-26 near Dollar Bay staring May 6th.
Contractors for the Michigan Department of Transportation will resume work on a culvert replacement project over a tributary of Gooseneck Creek.
MDOT is investing about $1.3 million to replace the structure, which was damaged during the severe flooding last June.
Last year, the culvert was installed; now, roadway reconstruction, paving, and guardrail work will be completed.
Work was suspended for the season in early December.
Work is expected to be completed by mid-June.