More reliable power and transmission can be expected when two new generating plants in the Upper Peninsula are complete.
Governor Rick Snyder had a call to action in 2015 because he felt there was energy crisis in the UP.
“When we set out to develop our project we were looking for a few things; a clean power source, affordable, long–term and that’s what this technology does for us” Director of Upper Michigan Energy Resources Corporation (UMERC), Richard Rayborn.
The generating station is fueled by natural gas, which is a clean technology that is becoming more prevalent in the United States.
Rayborn says the amount of energy that will be produced is unlike anything the U.P. has seen before.
“We have seven engines, each engine has a net output of 18 megawatts. One Walmart would be equivalent to one megawatt so, you could theoretically power 182 Walmarts with the engines that we have on site here” said Rayborn.
With the opening of the power plant around the corner many may be worried about how the Presque Isle Power Plant will be affected.
Rayborn said, “So our plans all along have been to close Presque Isle Power Plant, that’s still our plan. We would look to sync the commercial operation date with this facility with the closing of Presque Isle Power Plant, which would be sometime by mid–year next year.”
The change from the Presque Isle Power Plant to this new facility will be almost unnoticeable to consumers.
“There will not be any interruption of any kind. It will be synonymous, slowly taking down Presque Isle Power Plant and powering up this facility,” said Rayborn.
This station is currently at 45 percent completion and once this and the Baraga station are complete, Rayborn says they will be able to provide a long–term energy solution for the Upper Peninsula.
The power plant hopes to be fully operational by April 2019.
See the original story and video by ABC-10’s Caylee Kirby here.